Sub grade and pointing question

Patio flagstones (slabs), concrete flags, stone flags including yorkstone and imported flagstones.
Post Reply
ChrisHig
Posts: 4
Joined: Mon May 31, 2010 4:05 pm
Location: Swansea

Post: # 54899Post ChrisHig

Been doing lots of reading on here but the more I read the more confused I get so hope you don't mind me asking a few questions.

Have some 450x450 riven slabs on a small path.
Sub grade: under the top soil is a clay level but I've taken that down too far. Can it be replaced and compressed down (by hand?) for the bedding layer to rest on?

Pointing: from what I've read it needs to be done as soon as possible after laying the slabs. I won't have time to lay them all in one day so does that mean it needs to be done as I'm going along or can it all be done afterwards? Some people seem to recommend materials other than 4:1 mortar. Does that dry light or dark grey?

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 54918Post seanandruby

you need to replace it with a sub base leaving room for 40ml of bedding. For a small job like yours it would be cheaper to use mortar.
sean

GB_Groundworks
Site Admin
Posts: 4420
Joined: Sat Aug 09, 2008 3:55 pm
Location: high peak
Contact:

Post: # 54919Post GB_Groundworks

the colour of the mortar depends on the cement and the sand, all have different variations of shades from different quarries and different cements
Giles

Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.

http://www.gbgroundworks.com

London Stone Paving
Posts: 2199
Joined: Mon May 10, 2010 1:07 pm
Location: Surrey
Contact:

Post: # 54920Post London Stone Paving

Chris

1. Replacing the clay should be ok. Make sure its well compacted down though. You should also put down a layer of MOT type 1 and then run a whacker plate over it.

2. If you want to maintain a pointing colour, then have a look at Easipoint or romex which are both available in a darker shade.

3. The reason for pointing soon after paving is so that the pointing mix and the bedding layer set together and form a stronger unit. So in that respect it would be better off to point the sections as you go.

Hope that answers all your questions

ChrisHig
Posts: 4
Joined: Mon May 31, 2010 4:05 pm
Location: Swansea

Post: # 54934Post ChrisHig

The path is on an incline, maybe 20°. Would that change affect the sub base required? 40-50mm sub base with 40-50mm bedding?

So if I lay a few slabs one evening and point those, it'll be fine to lay more slabs another day and continue pointing those?

Thanks for all the help

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 54939Post seanandruby

if I ever overdig on anything I always replace with a hardcore, or dtp1. Subsoil, in my opinion, once out should stay out. ???
sean

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 54940Post lutonlagerlout

^^ what he said
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE