Small obstruction in inclined screed bed
-
- Posts: 2
- Joined: Tue Aug 03, 2010 1:17 pm
- Location: cheshire
Hi,
congrats first on probably the best trade specific website I've ever come across.
I am putting Tegula Drivesett blocks down on a path 2mx1m at the front of my Victorian house (foot traffic only). It is on a slight incline, with an upstand for the coal chute step at the top, a small step at the lower pavement level, and concrete edgings either side. I have already laid some MOT type 1, however with the bad weather, water is pooling at the bottom, next to the pavement border step. After reading this site, I realise I need at least 3-4 days of good, dry weather before screeding, as the Type 1 is fairly spongey.
My question is : at the top of the new path, the build-up of the existing coal chute has a little step that will be just covered by the sand, however could present a problem when compacting the sand. This is because I would expect the sand to compress at different rates due to the hard obstruction close to the surface...? Has anyone come across this before, or should a good pre-compaction regime negate any big differences ??
Hope all this makes sense...
Thanks
congrats first on probably the best trade specific website I've ever come across.
I am putting Tegula Drivesett blocks down on a path 2mx1m at the front of my Victorian house (foot traffic only). It is on a slight incline, with an upstand for the coal chute step at the top, a small step at the lower pavement level, and concrete edgings either side. I have already laid some MOT type 1, however with the bad weather, water is pooling at the bottom, next to the pavement border step. After reading this site, I realise I need at least 3-4 days of good, dry weather before screeding, as the Type 1 is fairly spongey.
My question is : at the top of the new path, the build-up of the existing coal chute has a little step that will be just covered by the sand, however could present a problem when compacting the sand. This is because I would expect the sand to compress at different rates due to the hard obstruction close to the surface...? Has anyone come across this before, or should a good pre-compaction regime negate any big differences ??
Hope all this makes sense...
Thanks
TH
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 2598
- Joined: Wed Apr 08, 2009 8:01 am
- Location: Peoples Republic of Westhoughton
- Contact:
and if the MOT is like slurry I would not go near it with a vibrating plate, like Luton says mix a 4:1 grit sand and cement and us this as your laying course
this might sound primitive but it works, seeing its only a small area so you can either use your feet, a piece of 4 x 2 timber and a lump hammer or a steel trowel to compact the mixture
then screed it to the correct level and fall and lay your block paving including all the cuts, put kiln dried sand into the joints, using the 4 x 2 timber placed on the blocks and tap gently using the lump hammer, you will see the kiln dried sand disappear as you do this so you may need to add more kiln dried sand
this might sound primitive but it works, seeing its only a small area so you can either use your feet, a piece of 4 x 2 timber and a lump hammer or a steel trowel to compact the mixture
then screed it to the correct level and fall and lay your block paving including all the cuts, put kiln dried sand into the joints, using the 4 x 2 timber placed on the blocks and tap gently using the lump hammer, you will see the kiln dried sand disappear as you do this so you may need to add more kiln dried sand
Crystalclear
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways
-
- Posts: 109
- Joined: Tue Jun 22, 2010 6:34 pm
- Location: manchester
- Contact:
??? if they are Tegula, dont hit them too hard ???
we are a paving & landscaping company serving the manchester and surrounding areas, we are marshalls approved installers and are happy to assist you in achieving your perfect Driveway or Patio
www.hawkpaving.co.uk
www.hawkpaving.co.uk
-
- Posts: 2
- Joined: Tue Aug 03, 2010 1:17 pm
- Location: cheshire
-
- Posts: 2598
- Joined: Wed Apr 08, 2009 8:01 am
- Location: Peoples Republic of Westhoughton
- Contact:
every job I do is assessed individually for the ground conditions and is completed the best possible way even if it means doing it an unconventional way
Crystalclear
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Site Admin
- Posts: 8346
- Joined: Mon Jul 05, 2004 7:27 pm
- Location: Warrington, People's Republic of South Lancashire
- Contact:
The problem you've correctly identified regarding the compaction of sand over the existing concrete and the newly placed sub-base is a knock-on effect of differential settlement. When you have laying course material over a rigid base, it will settle (or compact) to a different extent than it would over a flexible sub-base. This is the main reason why concrete bed is trimmed away from the 'front' face of edge courses and kerbs, so that the blocks (or flags or whatever) are lying on a full bed of laying course material, and not having one edge on a rigid bed.
While the cementitious screed option outlined by Mick and Luton et al is OK for smaller areas, the other strategy is to use trial and error to get the sand laying course to the correct depth and compaction to accommodate the blocks perfectly. This may take three, for, five or more attempts, and is the reason many contractors would opt for the cementitious screed option which they can get right(ish) first time in most instances.
Flexible *is* the correct construction for 99% of block paving work, but, as in life, there are always exceptions.
While the cementitious screed option outlined by Mick and Luton et al is OK for smaller areas, the other strategy is to use trial and error to get the sand laying course to the correct depth and compaction to accommodate the blocks perfectly. This may take three, for, five or more attempts, and is the reason many contractors would opt for the cementitious screed option which they can get right(ish) first time in most instances.
Flexible *is* the correct construction for 99% of block paving work, but, as in life, there are always exceptions.
Site Agent - Pavingexpert
-