hi everyone, ive had 20 tonne of limestone mot1 delivered today however due to a couple of light showers the last two days the sub grade is wet and muddy to walk on, you dont sink in it but if i dug my heel in i could probably push it in at least 20mm or so, is this too wet to start laying the mot 1? should i wait a couple of days for it to dry out?
-
- Posts: 393
- Joined: Fri Jun 13, 2008 6:20 pm
- Location: bolton lancs
- Contact:
-
- Site Admin
- Posts: 4732
- Joined: Fri Jul 28, 2006 8:47 pm
- Location: Somerset
- Contact:
I'd whack 100mm or so in to start with, give it a dry day or so, whack it and see how you go. If time is against you give it a whack right away as ambient says, you might be OK.
Chances are you'll be fine
Chances are you'll be fine
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset
See what we get up to Our Facebook page
See what we get up to Our Facebook page
-
- Posts: 32
- Joined: Thu Apr 17, 2008 5:05 pm
- Location: uk
- Contact: