Question regarding deposit??

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
GB_Groundworks
Site Admin
Posts: 4420
Joined: Sat Aug 09, 2008 3:55 pm
Location: high peak
Contact:

Post: # 36723Post GB_Groundworks

got a job to do and its only a couple of days work but the material costs for the security fencing is about 80% the job, and no account with supplier so can't get 30 days. we normally work on 25% upfront, then defined stage payments.

but with having never worked for the guy don't know if he'll stiff me, so wondering do i ask for more upfront to cover myself? not the way we normally work to ask for full payment upfront? Does anyone do this, like double glazing, conservatories etc?

erm, opinions please gentlemen?

gi
Giles

Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.

http://www.gbgroundworks.com

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 36731Post lutonlagerlout

the fact you are asking shows that you have bad vibes off this guy
it never hurts to ask giles
LLL :)
"what,you want paying today??"

YOUR TEXT GOES HERE

ambient
Posts: 393
Joined: Fri Jun 13, 2008 6:20 pm
Location: bolton lancs
Contact:

Post: # 36733Post ambient

i normally take people on face value if i dont trust them i take stage payments as i go, if i think they are ok i ask for 25% upfront rest when theyre satisfied dont usually go wrong, something like that fencing or anything non stock i would ask for payment for it on delivery or let them pay for it just order it for them ???
ambientdriveways.co.uk ambientexcavations-bolton.co.uk

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 36766Post Tony McC

If I don't feel comfortable with the client, then I want the whole of the materials cost before (cheque/BACS) or on delivery (cash only). No dosh: no materials.
Site Agent - Pavingexpert

Post Reply