Post: # 35073Post murraymint

I am trying to work out how much muck I am going to get if I excavate an area 5M wide X 3M long X 200mm deep. so I started by multiply the 5 by 3 and got 15 M Sq and then multiplied by .2 to get 3 cubic Meters.... is this right?

87-1235666499

Post: # 35078Post 87-1235666499

Sounds right but don't forget that if you have to remove it from site (unless you have time to ram it into a skip) you must add a bulk up factor of about 2.5 depending on the precise nature of the ground.

I screwed up badly once with the cost of grab lorries because of this.

WOP

msh paving
Site Admin
Posts: 1854
Joined: Tue Aug 19, 2008 7:03 pm
Location: kings lynn norfolk
Contact:

Post: # 35080Post msh paving

you will get around 6-7 tons depend on the material being dug out, should all go in a 8 yard skip MSH :)
paving, mini-crusher, mini-digger hire and groundwork
http://mshpaving.co.uk

Pablo
Posts: 1990
Joined: Sun Mar 25, 2007 10:49 pm
Location: N/Ireland

Post: # 35081Post Pablo

Technically yes but once excavated the volume will increase by anything from 1.3 to 1.6 times depending on the type of excavated material. This is only a guideline and can vary enormously if you add concrete etc into the equation. If it's normal earth multiply the solid cubic m by 1.5 and you'll get the close to the amount you'll end up with. If you're filling skips then layer it and foot stamp and you'll make it go a lot further. It should weigh approx 6.5 ton. These are all guesstimates and depending where you are and what you will be shifting could be way off.
Can't see it from my house

Pablo
Posts: 1990
Joined: Sun Mar 25, 2007 10:49 pm
Location: N/Ireland

Post: # 35082Post Pablo

Man I'm a slow typer you 2 beat me to it.
Can't see it from my house

msh paving
Site Admin
Posts: 1854
Joined: Tue Aug 19, 2008 7:03 pm
Location: kings lynn norfolk
Contact:

Post: # 35083Post msh paving

:D :D :D :D pablo
paving, mini-crusher, mini-digger hire and groundwork
http://mshpaving.co.uk

GB_Groundworks
Site Admin
Posts: 4420
Joined: Sat Aug 09, 2008 3:55 pm
Location: high peak
Contact:

Post: # 35099Post GB_Groundworks

Giles

Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.

http://www.gbgroundworks.com

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 35104Post lutonlagerlout

i normally just times by 2,so a 3 m3 hole fills a 6m skip
LLL