Concrete base for concrete sectional garage - Concrete base

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 27740Post Ramsay

This is my first ever post bit of a novice.
I have bought a concrete sectional garage about 18 ft x 8ft
Its going to be erected in my back garden on part of the grass this will take up about half of the grass.
Iam going to lift about half of the grass then put down a sub-base then use a vibrating plate to flaten it.
Then hammer steel pegs into the ground with steel sheets for the frame work to hold the concrete in place the frame work will be 4 " high from the ground
What kind of dpm should i use and how much will it cost ?
I got a few quotes for the concrete from about £ 260 - £ 320 this is ready mix deliverd is this normal price
And whats the best method of getting a perfect flat surface when the concrete is poured in ?
Thanks

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 27743Post lutonlagerlout

1200 gauge visqueen polythene
concrete i would hazard a guess at 2 m3 which would be roughly £250
you need a piece of wood longer than the width of the shutter
as you barrow the concrete to its final resting place you spread witha shovel then tamp with this piece of wood till the tamp touchs the shutter both sides,then repeat in a reciprocating motion back and forth,when you are happy with say a 450 section move down to the next one ad infinitum
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 27746Post seanandruby

Depends on what finish you want IE, heavy tamp, light tamp, brush, or smooth trowel, power float etc;
sean

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 27747Post Ramsay

thanks for the reply guys :)
the dpm does this come up 4 " aswell before the concrete is poured or does this just cover the bottom of the base ?
Garage is getting used as workshop / garage would be good to get a smooth even base as possible
And what type of sub-base should i use and how much should i buy.

matt h
Posts: 607
Joined: Mon Jul 09, 2007 11:14 pm
Location: gosport

Post: # 27753Post matt h

dpc should come up, and if poss tuck back into wall . smoother finish would be by powerfloat, but as you are keeping costs down use a derby or plasterer,s float to finish, subbase see mainsite
general builder, maintenance engineer, gas and plumbing installations, extensions etc

yourgardenworks.co.uk
Posts: 111
Joined: Wed Feb 20, 2008 1:25 pm
Location: Cumbria
Contact:

Post: # 27757Post yourgardenworks.co.uk

Ive just done the exact same thing in my own back garden. Iv'e used a 16 x 10 tarpaulin purchased from ebay for the grand some of £5 and i paid £165 for the concrete which was poured straight into the frame/shuttering, piece of piss as they say, took all of an hour too tamp then another hour to float out, easily good enough for a garage floor.

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 27763Post Ramsay

£165 thats a bargain the cheapest in glasgow i can get is £ 220
How much sub-base did you use ?

yourgardenworks.co.uk
Posts: 111
Joined: Wed Feb 20, 2008 1:25 pm
Location: Cumbria
Contact:

Post: # 27767Post yourgardenworks.co.uk

i used about 4 tonne mate, there is a calculator on the main site which will tell you what amount you need.

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 27799Post Ramsay

forgot to ask i have herd i should put oil on the seel shutter so that i can be removed easy when the concrete sets.
Is this true ? would this affect the concrete in anyway ?

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 27808Post Tony McC

Mould release oil (aka Soap Oil) is NOT the same as, say, engine oil or cooking oil.
Site Agent - Pavingexpert

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 27848Post Ramsay

Another question for the experts
I have just layed all my typer 1 down but i have not yet hired the vibrating plate yet.
Can i leave it like this for a while or iam i best using the vibrating plate as soon as.
I have coverd the area with plastic sheets

matt h
Posts: 607
Joined: Mon Jul 09, 2007 11:14 pm
Location: gosport

Post: # 27854Post matt h

best to compact in layers, but if you leave it a bit and then compact later cant see much harm:)
general builder, maintenance engineer, gas and plumbing installations, extensions etc

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 28267Post Ramsay

I have now used vibrating plate does this look ok for me to put shutter up now bit of a novice never done this before.

Image

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 28276Post lutonlagerlout

looks fine m8,well done
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

Ramsay
Posts: 16
Joined: Thu May 01, 2008 8:37 pm
Location: Scotland

Post: # 28554Post Ramsay

Image

Shutter up
When i get the concrete in should i remove the corner supports so i can tap the concrete level ?