Cement ballest sub base?? - Please need advice

All forms of block paving, brick paving, flexible or rigid, concrete or clays, new construction or renovation
Post Reply
woodpecker
Posts: 2
Joined: Tue Jan 15, 2008 10:21 am
Location: hants

Post: # 25299Post woodpecker

Hi I am having my block paving done about 60sq mtrs. I thought type 1 scalpings were laid below the sand screed but the guys doing have dug it out and say the best way to go is with a 5" ballest and cement dry mix which will be wackered down to give me a solid base, before they put on a sand screed.

My concerns are will this be as solid a base as type 1 and although the drive does have a good slope on it will the water drain as well.

Are they doing this to save money as will the cost of type 1 scalpings be more than cement and ballest..

Please Help..

steve wilkin
Posts: 11
Joined: Thu Jan 08, 2004 10:41 am
Location: north lincs
Contact:

Post: # 25300Post steve wilkin

i would have thought type 1 would be cheaper,plus sub-base should be free draining.

woodpecker
Posts: 2
Joined: Tue Jan 15, 2008 10:21 am
Location: hants

Post: # 25303Post woodpecker

thanks for that but would the base be as firm as type 1

surreyhillslandscapes.com
Posts: 127
Joined: Mon Nov 05, 2007 5:37 pm
Location: Surrey
Contact:

Post: # 25304Post surreyhillslandscapes.com

Are they a paving company or builders ?
ooo0
( ) 0ooo
\ ( ( )
\_) ) /
(_/

I've just screeded that!!!!!!!

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 25385Post Tony McC

Using a hydraulically bound sub-base is done in an attempt to minimise settlement. However, if the contractors were to spend more time installing a proper flexible sub-base, and pay more attention to their screeding, edge course construction and cutting-in, there'd be a lot fewer instances of settlement.

I'm becoming increasingly concerned that bound sub-bases are being used by some so-called contractors in place of thorough construction and best practice. There are instances when a bound sub-base is justified, but these are the exception, not the rule.

If a bound sub-base is used, there are problems regarding drainage of the laying course, as discussed on this page
Site Agent - Pavingexpert