Screeding round manhole covers - A few questions!
-
- Posts: 8
- Joined: Fri Nov 02, 2007 3:06 pm
- Location: Daan Saaf
Hi, getting towards the stage of screeding for my DIY block paved drive widening project. I have had to install a recessed manhole cover and have a query about how to screed round it.
Due to the recessed manhole cover being concreted in, the area directly around the manhole cover will have a more shallow screed depth (thickness of sharp sand) than the rest of the drive (I'm using 60mm blocks and there's about a 75mm gap between the top of the manhole cover level and the concrete fixings, leaving about 15mm of space for the sand).
How do I best deal with this in order to ensure the blocks over it remain level with all the other blocks and do not sink (or rather 'hump') due to the different screed depth? The concrete fixing extends about 50mm outwards if that helps.
Thank you, I'm all ears!
Cheers.
Due to the recessed manhole cover being concreted in, the area directly around the manhole cover will have a more shallow screed depth (thickness of sharp sand) than the rest of the drive (I'm using 60mm blocks and there's about a 75mm gap between the top of the manhole cover level and the concrete fixings, leaving about 15mm of space for the sand).
How do I best deal with this in order to ensure the blocks over it remain level with all the other blocks and do not sink (or rather 'hump') due to the different screed depth? The concrete fixing extends about 50mm outwards if that helps.
Thank you, I'm all ears!
Cheers.
-
- Posts: 127
- Joined: Mon Nov 05, 2007 5:37 pm
- Location: Surrey
- Contact:
I would screed as normal running the block around the cover 5 to 10mm above, if they are sitting a little proud after compaction then maybe a little gentle persuasion with a rubber mallet, little tip, use tractor grease between the cover and frame, it stops too much kiln dried getting in the gap and make it a lot easier to get out should you need to.
ooo0
( ) 0ooo
\ ( ( )
\_) ) /
(_/
I've just screeded that!!!!!!!
( ) 0ooo
\ ( ( )
\_) ) /
(_/
I've just screeded that!!!!!!!
-
- Posts: 884
- Joined: Thu Feb 08, 2007 12:28 pm
- Location: Reading
Rather than have the blocks half-on half-off the rigid base around the MH, consider laying the solids and cuts to the rim on a mix. It will make the sand prep up to these blocks a bit tricky, but you don't want a block with 15mm of sand under on one side and 40-50mm on the other.
Per the above, the blocks laid on the full sand bed need to be proud of the concreted ones, but 5mm is enough I'd say
Per the above, the blocks laid on the full sand bed need to be proud of the concreted ones, but 5mm is enough I'd say
-
- Posts: 8
- Joined: Fri Nov 02, 2007 3:06 pm
- Location: Daan Saaf
-
- Posts: 127
- Joined: Mon Nov 05, 2007 5:37 pm
- Location: Surrey
- Contact:
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
good question and i have asked many people this before without a satisfactory answer
i suppose unless you can get a cover with 150mm profile so that sand is even you will always get some lumping after a few years
all the above fixes are short term ,but i suppose most important is to make sure you use terram and make sure your sub base is well compacted to alleviate any settlement
good luck
LLL
i suppose unless you can get a cover with 150mm profile so that sand is even you will always get some lumping after a few years
all the above fixes are short term ,but i suppose most important is to make sure you use terram and make sure your sub base is well compacted to alleviate any settlement
good luck
LLL
-
- Posts: 127
- Joined: Mon Nov 05, 2007 5:37 pm
- Location: Surrey
- Contact:
-
- Posts: 20
- Joined: Mon Aug 20, 2007 7:57 pm
- Location: Cambridge
Front drive going well; wish I had more time to get on with it.
I read the forum topic on screeding around manholes and have read the section on recessed trays.
Are there two schools of thought on when to install the tray/manhole?
The site topic discusses putting in the recessed tray once it is already virtually surrounded by blocks (using the surrounding blocks to give the manhole level) whilst the forum seemed to be discussing putting the tray/manhole in first.
I am about to install a recessed tray.
I have already completed the border blocks around the whole drive area and had intended putting in the tray next before I started to do any screeding and blocking.
Can someone indicate what would be the best time to do the tray/manhole?
Many thanks
De1b0y
I read the forum topic on screeding around manholes and have read the section on recessed trays.
Are there two schools of thought on when to install the tray/manhole?
The site topic discusses putting in the recessed tray once it is already virtually surrounded by blocks (using the surrounding blocks to give the manhole level) whilst the forum seemed to be discussing putting the tray/manhole in first.
I am about to install a recessed tray.
I have already completed the border blocks around the whole drive area and had intended putting in the tray next before I started to do any screeding and blocking.
Can someone indicate what would be the best time to do the tray/manhole?
Many thanks
De1b0y
Delboy
-
- Posts: 368
- Joined: Tue Sep 25, 2007 7:20 pm
- Location: darwen
- Contact:
-
- Site Admin
- Posts: 4732
- Joined: Fri Jul 28, 2006 8:47 pm
- Location: Somerset
- Contact:
Yep, that's the way I'd be doing it tooJames.Q wrote:lay blocks then fit man hole cover works every time
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset
See what we get up to Our Facebook page
See what we get up to Our Facebook page
-
- Posts: 20
- Joined: Mon Aug 20, 2007 7:57 pm
- Location: Cambridge
And then..........
OK first lay blocks surrounding manhole position, then install manhole.
But.........
Following on from earlier comments in this posting, should the final blocks surrounding the manhole be laid on a bed of mortar? Otherwise one end of these blocks will be sitting on the 'haunches' and the other on the compacted screed.
Regards
De1b0y
OK first lay blocks surrounding manhole position, then install manhole.
But.........
Following on from earlier comments in this posting, should the final blocks surrounding the manhole be laid on a bed of mortar? Otherwise one end of these blocks will be sitting on the 'haunches' and the other on the compacted screed.
Regards
De1b0y
Delboy
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
If you haunched it correctly it shouldn't. Your haunching should be angled so that you can lay on a continuous bed. May be easier to break out the surround and redo it. At least you only have one manhole to do, Ive been on jobs were bods have backed kerbs up so high that hundreds have had to be reduced to accommodate paving. Is the haunching to wide for you to undercut the blocks?
sean
-
- Posts: 20
- Joined: Mon Aug 20, 2007 7:57 pm