About 90m of concrete post and featheredge!
Recently completed 2km of digging off wooden footpath edgers and replace with 150*50 PCC edgers and resurfaced the footpaths - now that got tedious after the first two weeks..........
Recently completed 2km of digging off wooden footpath edgers and replace with 150*50 PCC edgers and resurfaced the footpaths - now that got tedious after the first two weeks..........
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset
See what we get up to Our Facebook page
See what we get up to Our Facebook page
-
- Posts: 585
- Joined: Tue Aug 29, 2006 9:02 pm
- Location: Luanda, Angola
-
- Posts: 368
- Joined: Tue Sep 25, 2007 7:20 pm
- Location: darwen
- Contact:
-
- Site Admin
- Posts: 8346
- Joined: Mon Jul 05, 2004 7:27 pm
- Location: Warrington, People's Republic of South Lancashire
- Contact:
We re-aligned a road in St.Helens about 20 years ago, and from memory, that was around 1km, possibly 1.2km, which involved taking down a steel palisade fence that was 2.8 m high and re-erecting it 4 m back from the original line to make room for the widened road and school-kid friendly footpath that formed the main part of the job.
I only did a couple of days on it, setting out and establishing safety protocol, and then left one of my gangers to supervise most of the physical work. No point having a dog and barking yourself!
I only did a couple of days on it, setting out and establishing safety protocol, and then left one of my gangers to supervise most of the physical work. No point having a dog and barking yourself!
Site Agent - Pavingexpert
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 357
- Joined: Sun Oct 08, 2006 9:46 pm
- Location: Stoke
One of the Biggest jobs i've done was a 2.5 km fence, 8 foot steel palisade fence, during the Winter last year.
Was a right son of ***** aswell. knee deep in liquid mud. Post holes filling with water, Concrete taking over 2 weeks to set hard enough.
The Conditions were atrocious (sp?) we got our 5 tonne Terex site dumper stuck. Had the Wrong gates delivered. etc etc.
Cost over £100,000 apparently. and by all accounts, the Main gates have only just been fitted.
Was a right son of ***** aswell. knee deep in liquid mud. Post holes filling with water, Concrete taking over 2 weeks to set hard enough.
The Conditions were atrocious (sp?) we got our 5 tonne Terex site dumper stuck. Had the Wrong gates delivered. etc etc.
Cost over £100,000 apparently. and by all accounts, the Main gates have only just been fitted.