Wacking - Best done wet or dry?

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
GeoffV
Posts: 1
Joined: Fri Jul 20, 2007 4:56 pm
Location: South East

Post: # 20880Post GeoffV

Have got to wack about 112 sq m. of type 1.
With the weather the way it is at the moment just wondered if being wet will reduce the efficiency of the wacking.
Will it take more passes?
All advice gratefully appreciated.

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 20887Post Tony McC

No significant difference. Compaction is supposed to be done when the aggregate has what is deemed to be an optimum moisture content. This means that aggs can be too wet or too dry for optimum compaction, but, in all honesty, unless you were building a critical pavement such as a motrorway or airport runway, I wouldn't worry to much about it.
Site Agent - Pavingexpert