Moving an oak-framed garage - Best way to do it?

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Ted
Posts: 585
Joined: Tue Aug 29, 2006 9:02 pm
Location: Luanda, Angola

Post: # 20201Post Ted

Image

I want to move a garage similar to this, except this one is three bay with a log store on the side.

Has anyone ever tried moving one before?

The garage is made by Border Oak...

http://www.borderoak.com/

My plan was to lift it up somehow on a couple of tractors and move it to its new position but the ground is not perfectly level so I don't know how well this plan would work.

Some people tell me to take it to pieces and rebuild it but others say it will never go back together very well.

I supposed I might be able to lift it up with a crane and move it...

Has anyone tried moving a garage similar to this?

What method did you use?

Did it work well, or not?

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 20218Post Tony McC

I've never moved owt like that, but the one thing I do know about moving structures such as this is that lifting and shifting completely changes the direction of forces for which they are designed. A structure can be incredibly strong when sat there, in compression due to gravity, but as soon as you attempt to lift it from the top, it goes into tension and falls apart.

So: all I can suggest is finding some way of fixing the lifting points at the base of the structure so that it remains in compression during the move.
Site Agent - Pavingexpert

steve r
Site Admin
Posts: 143
Joined: Tue Jan 28, 2003 9:18 pm
Location: chelmsford

Post: # 20220Post steve r

Problem with an oak framed building is all the joints will be pegged, so taking it apart will be a problem.
Lifting will also be difficult as Tony says.
The centre support at the front sits on a stone block and when you lift it will leave the front of the roof unsupported.
Although I have assembled one of these buildings I have not attempted to move one.
Maybe you could bolt a length of timber across the front and put your strops under that.




Edited By steve r on 1182938987
Steve Rogers

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 20252Post lutonlagerlout

well i would have thought you need a crane at least ,theres £5-700 gone
then as the gaffer says things lifted like that have a tendancy to fall apart
no way of stripping the roof and taking it down and rebuilding?
LLL ???
"what,you want paying today??"

YOUR TEXT GOES HERE

andpartington
Posts: 308
Joined: Sat May 27, 2006 9:19 pm
Location: cheadle uk

Post: # 20274Post andpartington

drop a match on a pile of oily rags and scrap timber petrol can ect and get a new one on the insurance and get it put where you need it if its time for a new truck stick it under as well :d
or get some chavs to chuck the match on
how far does it have to go?

andy
Warning "Dyslexic Fingers At Work" in Cheadle, Manchester UK
cheers andy

dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 20279Post dig dug dan

you have to jack the building up and slide long rsj's under each set of legs so the stick out beyond the building. The crane can then attach to these to lift, and plce in its new position.
This is how I have seen it done before
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

Ted
Posts: 585
Joined: Tue Aug 29, 2006 9:02 pm
Location: Luanda, Angola

Post: # 20284Post Ted

lutonlagerlout wrote:no way of stripping the roof and taking it down and rebuilding?
LLL ???
Well we could, but I have been told by some sources that as it is Oak it will never go back together quite as well but others say taking it down is not a problem...

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 20288Post lutonlagerlout

i would have thought its a days work for 3 blokes dismantling it so theres £450 ish
and 2 days rebuilding it at least so theres £1500 that way
with a crane you need a banksman and a lot of luck
decisions decisions
dont you get any straightforward jopbs ted???????

saying that we started a job in harpenden today and straightaway, i spotted an 8 M pine tree 2 m away from the proposed wall
BCO came out and said "lets start at 2.5m deep and see what we find"
always get these low access no-brainers???
lol
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 20293Post seanandruby

jack it up and put "strong backs" underneath then hire a large forklift. strong backs by RMD falsework. :;):
sean

Dave_L
Site Admin
Posts: 4732
Joined: Fri Jul 28, 2006 8:47 pm
Location: Somerset
Contact:

Post: # 20320Post Dave_L

Anybody watch "Mega Movers" on Sky?

Best get them over from the USA to do the job.

Could be expensive ;)
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page

IanMelb
Site Admin
Posts: 417
Joined: Wed Apr 11, 2007 11:53 am
Location: East Riding

Post: # 20322Post IanMelb

I saw one a while back - might have been mega movers. They were moving a grain silo about 20 miles in the Rockies. This thing was about 6 stories high ...

Dave_L
Site Admin
Posts: 4732
Joined: Fri Jul 28, 2006 8:47 pm
Location: Somerset
Contact:

Post: # 20326Post Dave_L

Yeah that's it - some of the moves they do are very dodgy! They seem to have a fairly good success rate though.....
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 20350Post seanandruby

have you seen the bridge over the runway at gatwick? we built that landside then moved it airside. took a week to get it in place. :cool:
sean

matt h
Posts: 607
Joined: Mon Jul 09, 2007 11:14 pm
Location: gosport

Post: # 20659Post matt h

H aving costructed several oak framed structures, it is probablly best to dismantle and rebuild, due to the inherent stresses created trying to lift them. May have to make new pegs and replace some tiles, but at least the structure will remain intact. I know its time consuming but at least you wont be paying out for replacement beams.etc
general builder, maintenance engineer, gas and plumbing installations, extensions etc

Ted
Posts: 585
Joined: Tue Aug 29, 2006 9:02 pm
Location: Luanda, Angola

Post: # 20665Post Ted

seanandruby wrote:have you seen the bridge over the runway at gatwick? we built that landside then moved it airside. took a week to get it in place. :cool:
I haven't been to Gatwick for a few years but is it sensible to have a bridge over a runway!? ???

Post Reply