Hi, I'm just about to start a DIY paving project.
I want to do my drive in clays but I'm worried about movement.
My house is built on the site of an old victorian baths and I'm in the deep end .
My neighbour dug a test pit to see how far the his footings were down and had a shock at 32 courses! below the DPC.
All the backfill was topsoil which explains why when I built a 6ft boundary wall between our properties 3 yrs ago it's sunk by 1 1/2".
The drive has normal traffic, with occasional use by a 7 1/2 tonner.
Should I go for a deeper sub base than normal? Or is there anything else I should be considering.
cheers guys.
morsefull

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 18878Post lutonlagerlout

32 course isnt especially deep footings ,its about 2.5 m i did work in london in the early 90s and sometimes there were 40 course in the footings depending on the site datums
if you dig out maybe 350 mm below finished then use terram ,then 150mm of type 1 ,then wack,then 120 mm of type 1 then wack,then sand blocks etc
remember block paving is a flexible drive so even after this if it sinks an inch in 5 years ,you can always take the clay pavers up and do it again
mind you this is only what i would do ,a structural engineer would give you the full rundown
cheers LLL :)
"what,you want paying today??"

YOUR TEXT GOES HERE

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 18937Post Tony McC

LLL is right - excavate to around 500-600mm and use a geotextile over the sub-grade. Place, level and compact approx 150-200mm of Type 1 using a vibrating roller or a big, heavy plate compactor. Then, place a layer of geo-grid, and overlay that with another 150mm or so of Type 1. The geo-grid will substantially reinforce your sub-base and minimise any settlement for several years.

For an example of a geo-grid, see this site ... other geo-grids are available.
Site Agent - Pavingexpert

morsefull
Posts: 2
Joined: Fri Feb 02, 2007 5:41 pm
Location: staffs

Post: # 18952Post morsefull

Thanks guys, this site is so good .
It's nice to see that people are willing to help out with advice for us novices.
I feel fairly confident of getting a good result having read your replies.
Now to start sourcing materials.
:)
morsefull

Dave_L
Site Admin
Posts: 4732
Joined: Fri Jul 28, 2006 8:47 pm
Location: Somerset
Contact:

Post: # 18961Post Dave_L

Keep us posted (pics would be good) as to how you get on, Morse (please)
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page