I understand that machine lay will produce superior results.
Is there minimum number of Meters2 to be covered before machine lay is an option?
Monsoon
Machine or hand lay tarmac?
-
- Site Admin
- Posts: 4732
- Joined: Fri Jul 28, 2006 8:47 pm
- Location: Somerset
- Contact:
Yes - although it is variable....
You have to take into account the haulage costs etc - this is largely dependant upon how for the machine has to 'travel' to you.
We have machine laid jobs locally to us where it would be uneconomical for a contractor further away to do the job, if you see where I'm coming from.
Yes - machine laid surface will be far superior (in the hands of a good crew, anyway!) but don't be put off by hand laid material.....
You have to take into account the haulage costs etc - this is largely dependant upon how for the machine has to 'travel' to you.
We have machine laid jobs locally to us where it would be uneconomical for a contractor further away to do the job, if you see where I'm coming from.
Yes - machine laid surface will be far superior (in the hands of a good crew, anyway!) but don't be put off by hand laid material.....
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset
See what we get up to Our Facebook page