For my patio the sub base will be 50mm type 1 MOT.
What depth should it be before putting the wacker plate over it to compact to the required 50mm?
Thanks
Type 1 depth pre-wacking
-
- Site Admin
- Posts: 417
- Joined: Wed Apr 11, 2007 11:53 am
- Location: East Riding
Re: Type 1 depth pre-wacking
I can't necessarily answer your query, but could I just clarify your question - do you mean - "What depth of *loose* type 1 will compact down to 50mm?"
-
- Posts: 2
- Joined: Wed May 22, 2024 11:13 pm
Re: Type 1 depth pre-wacking
Hi - yes, that. What loose depth will compact to 50mm
Thanks
Thanks
-
- Site Admin
- Posts: 417
- Joined: Wed Apr 11, 2007 11:53 am
- Location: East Riding
Re: Type 1 depth pre-wacking
As I say, I don't think that I can answer your direct query, but I used the calculators on the main site to get the quantity of MOT for a specific (final) depth. Then threw all the tonnage in to the hole, spread it out evenly and compacted it down