I'm in the process of laying my own 55 sqm block paved driveway and am at the bedding layer stage. Following the advice on this site I intend to use the pre-compaction method
Due to time constraints I'm unable to screed the sand and lay large areas of blocks at any one time. So my questions are ;
Is it ok to screed and lay blocks in small sections ?
Will the uncompacted blocks be able to sustain light foot traffic for a few days ?
I know its not ideal, but I think I'm trying to take a bit of confidence from my hope that there must be driveways out there that have been successfully laid - despite doing parts of it arse about face.