Brickalying quantity - How many bricks per hour?

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 11253Post dig dug dan

I am pricing a landscaping job at the moment, and as I am not a bricklayer, I sub out any bricklaying.
The wall is 16.5m on a curve, will be 1.5m high, and will be freestanding, i.e. not a retaining wall, therefore, facing bricks both sides
According to my calculations, thats 2970 bricks.
Assuming the bricklayer has a mate to mix and hod, how long would this expect to take? how many bricks can he feasably lay in a day/hour?

I have estimated 5days. am i way off the mark here?
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 11328Post Tony McC

60 bricks to the square metre and most 1+1 brickies would expect to lay a minimum of 10 square metres of facing work per day.
Site Agent - Pavingexpert