Hi. I'm about to start breaking up my concrete driveway ready for block paving. As this is going to be a diy job its going to take a long time so I'm looking for ideas as to what to put down over the excavated areas for the family to walk on for (a) safety and (b) to stop the kids walking chalk and mud into the house. I was thinking of putting down a couple of sheets of ply but think this could get a bit slippery. Any ideas appreciated. Thanks.John
John

rxbren
Posts: 394
Joined: Thu Jan 05, 2012 11:41 am
Location: northampton

Post: # 112069Post rxbren

Dig it out, lay your edgings and stone it up and compact it job done till you come to speed sand and lay blocks

Hawaii04
Posts: 42
Joined: Sun Mar 13, 2016 11:46 am
Location: Kent

Post: # 112070Post Hawaii04

Hi and thanks for the tip but from taking up the concrete to actually getting the edge down and mot type 1 is going to be a matter of months as I'll be doing this on my own and only on my days off. It's just to give people something safe to walk on that I can take up and down in between digging. Thanks anyway.
John

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 112071Post seanandruby

Could be that your concrete base is sat on a sound sub base, take a piece up and see. If not, You could break out where your edgings are going and set them in leaving enough existing concrete in for a footpath until you need to take the rest up. If you use ply you could cover with rough roofing felt as an anti slip.
sean

Hawaii04
Posts: 42
Joined: Sun Mar 13, 2016 11:46 am
Location: Kent

Post: # 112073Post Hawaii04

Thanks. Both ideas are great.
John

lemoncurd1702
Posts: 712
Joined: Sat Oct 19, 2013 7:56 am
Location: South Wales
Contact:

Post: # 112074Post lemoncurd1702

Or do it small chunks. Break and excavate 10m2 and base up leaving enough room to install edgings later. I would only partially lay the sub-base, maybe just the initial 75mm, top up later when the whole area is dug out to achieve correct levels.
Better still work your days off and save the extra money to pay a contractor to do it. If it takes a two man contractor 5 days it'll take you 15. Doing it yourself you're only going to save on the labour and probably pay more for the materials and waste disposal of etc.:p
Cheers
Lemoncurd

Hawaii04
Posts: 42
Joined: Sun Mar 13, 2016 11:46 am
Location: Kent

Post: # 112093Post Hawaii04

Yes I like the idea of doing 10 m2 at a time. I'll prob do that. Unfortunately I don't have the option of working on my days off and already have the blocks and materials so it's just my own time and disposal of excavated materials I've got to worry about. Lucky I'm in no rush to get this done and have a very patient mrs. Thanks for advice.
John