So, I've done some digging this weekend with a view to extending our patio. Aiming for 75-100mm drop for hardcore, 20mm for a dry sand and cement mix and then the slabs themselves. I've definitely overshot it in some places and not hit it where I couldn't get the spade in, which I hope is ok.
Anyway, I've counted approx. 70 600mm square slabs would be required to cover the new area. I think this is about 25m2.
Does 5 1m3 bags of hardcore seem sufficient to fill the sub base layer or obviously too little / too much? How much sand and cement would you expect?
Thanks in advance.
How much material?
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 42
- Joined: Thu Jun 16, 2016 4:23 pm
- Location: Shropshire, Cheshire, Oxfordshire
This should help you to calculate quants for laying http://www.pavingexpert.com/calcall.htm