This question has probably been asked many times, but I'm unable to find it!
I have laid a mot 1 sub base for my patio to a depth of 100mm.This layer is fairly well compacted and has sufficient fines to fill the gaps between the crushed stone. Its for light use only and has been leveled.

Do I now require another screed layer of sand before the bedding mortar layer of 10:1 sharp sand to cement, or can I go straight to the bedding mortar layer
Graham H

lemoncurd1702
Posts: 712
Joined: Sat Oct 19, 2013 7:56 am
Location: South Wales
Contact:

Post: # 104963Post lemoncurd1702

Straight to the bedding mortar. I've seen this layer of sand business in so many books over the years and never quite understood the point in it.
They were the same books that recommended laying on spots :p

Maybe go a bit stronger on you mix 8:1 at least.
Cheers
Lemoncurd

Grahamh8
Posts: 10
Joined: Tue Jul 14, 2015 6:06 am
Location: Oxford

Post: # 104965Post Grahamh8

Thanks for the advice.
Graham H

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 104977Post Tony McC

Yes, I too have seen the mystery 'intermediate sand layer' in some books about paving, and it is immediately apparent that such books were written by fools with no real experience and buggerall in the way of skills or understanding of pavement structure.

I suspect such a ludicrous construction was shown in an amateur guide many years ago and then a succession of copycat authors took it as gospel because they knew no better.

The *correct* methodology is shown on the main website.....