Hi, thanks to the great information on this site I'm almost ready to be laying my first patio. I will be laying 450x450 slabs on a full mortar bed and pointing between. It's quite a small area, about 10m^2, but as it's my first time I'll be fairly slow to make sure I get all the slabs laid perfectly, so it's going to take me more than a day to lay the slabs.
I thought it would be easier to get all the slabs set in place and then point the lot on another day but then I read here (http://www.pavingexpert.com/pointing.htm) that it's good to avoid a 'day joint' so does this mean it would be better to lay it bit by bit, pointing as I go?
Thanks in advance for your advice